Sprint Sand & Clay
Houston, TX 77224
Featured Project Return to Projects List
Stormwater Detention Basin – City of Houston Bretshire
Project Information
- Project Location:
- Houston, TX
- Status:
- In-Progress
- Structure Type:
- Misc Project
Scope Of Work
Sprint Sand & Clay completed the Bretshire Detention Basin for the City of Houston as the Prime Contractor. Contract amount for this project was $4,715,038.00, and Sprint was required to remove and legally dispose of 825,210 cubic yards of dirt in 400 calendar days. It is projected that the drainage improvements provided by this basin will positively affect 90,000 homes in the surrounding area where flooding has been a constant problem. Sprint Sand & Clay is an approved contractor with the City of Houston, Harris County and many other Municipalities in the Greater Houston Area.